Work on the new railway station in Hamburg is at a standstill, labeled as preposterous.
The construction of the Diebsteich long-distance and regional train station in Altona, Germany, is facing significant delays, according to recent updates. The project, which involves a nationwide scale of construction measures, is currently under review by the Senate, and it appears unlikely that the station will be fully operational by the end of 2027.
The ongoing construction at Hamburg Central Station and surrounding routes, with complex phased closures and night work continuing significantly into 2025, is one key factor contributing to the delays [1]. Furthermore, a recent report from the S-Bahn Hamburg website states that the opening of Diebsteich Station has been delayed since January 2025, with outstanding construction issues such as detected defects on a bridge near Holstenstraße necessitating line closures and affecting S-Bahn scheduling [2].
Another concern is the absence of tenders or procurement for platform construction at Diebsteich, which typically would be a prerequisite to meet any operational deadline. The lack of such tenders signals potential further schedule risks [3].
Heike Sudmann, the Left Party's spokesperson on transport, has expressed concerns about a potential year- or even decade-long temporary solution at the new Diebsteich station. The public-facing Info Center for Diebsteich, which opened in late 2024, indicates that much of the area and project planning is still underway rather than complete [3].
The impacts of these delays are still being evaluated, but it is reasonable to conclude that Diebsteich Station will likely not be operational by the end of 2027 under present conditions. The timeline for the completion of the station building is currently unclear.
Despite the challenges, the Diebsteich long-distance and regional train station project remains a significant infrastructure development, with the potential to greatly improve transportation in the Altona area. As the construction continues, updates and progress reports will continue to be closely monitored to assess the situation and provide the public with the latest information.
References: 1. Hamburg S-Bahn works update, 2025. 2. S-Bahn Hamburg website update, August 6, 2025. 3. Nahverkehr Hamburg portal, 2024.
- The delay in the completion of Diebsteich long-distance and regional train station is causing concern, as the project's timeline is currently unclear and it seems unlikely that the station will be operational by the end of 2027, given the ongoing issues such as missing tenders for platform construction and detected defects on a bridge near Holstenstraße.
- Amidst the delays and concerns, the Diebsteich long-distance and regional train station project continues to be a topic of general news, politics, and policy-and-legislation, as it represents a significant infrastructure development with the potential to greatly improve transportation in the Altona area.